June 15 | Just before they started digging. | |
June 15 | Cellar hole is almost complete. | |
July 18 | The driveway has been graded. | |
June 27 | Foundation footings have been poured. | |
June 30 | Footings have been filled. | |
July 7 | Erecting the foundation forms. | |
July 7 | Pouring the foundation. | |
July 8 | The foundation has been waterproofed. | |
July 12 | Backfilling around the foundation. | |
July 13 | Drilling the well. | |
July 13 | Highly sophisticated well flow measurement. | |
July 17 | Highly sophisticated frac results measurement. | |
July 18 | We got the building permit... a week late. | |
July 18 | 1st delivery of wood (in the garage!). | |
July 19 | Framing begins. | |
July 20 | Great progress in just a day. | |
July 20 | The underside of the floor framing. | |
July 21 | 1st floor deck complete (and it rained). | |
July 21 | The front of the house. | |
July 24 | 1st floor front walls are up. | |
July 28 | Garage framing begins. | |
July 28 | 1st floor interior walls are added. | |
August 3 | More rain, the house is a lake. | |
August 5 | Adding the 2nd floor deck. | |
August 18 | Garage ceiling framed. | |
August 22 | The back of the house. | |
August 22 | The front of the house. | |
August 24 | Lally columns replace temporary supports. | |
August 25 | Starting to build the 2nd floor walls. | |
August 28 | 2nd floor exterior walls complete. | |
August 31 | 2nd floor interior walls complete. | |
September 5 | Garage gables framed. | |
September 6 | Garage roof framed. | |
September 8 | Garage roof plywooded. | |
September 11 | 1st floor roof (what there is of it!) framed. | |
September 27 | Framing the 2nd floor roof. | |
October 3 | 2nd floor roof framing & plywood almost done. | |
October 3 | The back side of the house. | |
October 10 | Starting to frame the front porch. |